GENERAL CONSTRUCTION

Case Study: Hannover St, Manchester

Overview:

Our client approached us to restore the appearance of the building on a main street in Manchester which had become dilapidated due to weather and plant growth.

The building was also suffering from leaks because of a poor-condition slate roof.

The contract involved the erection of a full scaffold around the building, incorporating safe walkways for pedestrians due to the pavements having to stay accessible below.

We removed all plant growth and treated the affected areas before completing adequate roof repairs to overcome the present leaks.

Existing mortar was removed to all block and brickwork faces leading to a full repoint. A full acid wash was carried out to all masonry to restore it to its original condition, the existing sash windows were sanded and repainted before being fully reseal.

The Facts:

LOCATION: Hannover St, Manchester

CLIENT: Hyde Estates

CONTRACT VALUE: £60,000

PERIOD: March – April 2021

CONTRACT PERIOD: 8 Weeks

More Images of the Project

Case Study: Hazel Wood High School

Overview:

The scope of works involved converting an existing classroom within the school into a new communal unisex toileting block. This was because the existing separate toilets were regularly vandalised.

The existing classroom was removed and existing drains were located. We then installed two new drainage chambers to accept all new waste drainage routes from the new toilets and sinks.

Block walls were erected to separate the maintenance cupboards where the chambers were located to the main toileting locations with lockable fire door access.

The existing entrance to the toilets was opened to allow wider access from the main hallway routes.

New vinyl floors and a false ceiling were included as well as a full repainting.

The existing toilets were removed including all block walls to create a new music classroom, some store rooms, and two office areas.

All areas included the installation and alteration of a new electrical layout to suit the new room uses.

The Project was completed within the six-week summer holidays ready for the return of pupils in the new term.

School Bathroom refit

The Facts:

LOCATION: Hazel Wood High School

CLIENT: Elms Trust

CONTRACT VALUE: £120,000.00

PERIOD: August – September 2022

CONTRACT PERIOD: 6 Weeks

More Images of the Project

Quote Request Form

If you’ve got a general construction project that you want completed, we’re the team for the job.

We’ve completed hundreds of construction projects at all scales, from the small to massive.

If you’d like a competitive quote for your work, reach out using this form and we’ll be in contact as soon as possible. 